Construction Updates

Exterior Progress

  • All exterior finishes will be completed in April in preparation for sidewalks, final grading, and pavement installation.
  • Metal paneling, caulking, and exterior painting will be completed in April.
  • Aluminum window frames will be finished early April, with glass installation continuing throughout the month.
  • Roof coping installation will be finalized.
  • Masonry work is complete, and all masonry will be washed in early April.

Interior Progress

  • Painting is underway, with final touch-ups and coats scheduled to be completed in May.
  • Flooring installation is complete in the childcare, healthcare, and community center management areas.
  • Casework installation has begun in key areas: childcare, health department, and management offices.

Interior Progress

Pool & Recreation Updates

  • Lap Pool and Leisure Pool are currently undergoing water testing, and finishes will begin soon.
  • Mechanical systems for the pools are being built and connected.
  • All gym equipment is installed; final electrical connections are in progress.
  • The playground contractor will begin constructing the two-story playground structure.

Systems & Utilities

  • Underground utility work, concrete, and site grading continue across the property.
  • Permanent power has been established throughout the building.
  • Final electrical and mechanical connections are being made; equipment start-ups are being scheduled.
  • Elevator installation will be completed soon.

Latest Drone Footage of Construction Site

Latest Drone Footage of Construction Site

Systems & Utilities

Sign Up for Pre-Sale Charter Memberships

Sign up a for membership to the Fishers Community Center.