June Construction Updates
Road & Site Work
- Hoosier Road & 121st Street Roundabout:
- The intersection is now closed for roundabout construction.
- Closure Duration: May 29 – August 5 (HSE summer break).
- This is a full intersection closure to accelerate construction.
- The roundabout will include raised and striped pedestrian crossing speed tables on all four legs, ensuring safe access for pedestrians and cyclists entering the campus.
- Site Grading & Landscaping:
- Crews are using heavy equipment to complete final grading, install underground utilities, plant trees and landscaping, and begin irrigation installation.
Aquatics Center Progress
- The pool slide has been installed on the exterior of the building.
- Tile work and mechanical component installation for the pools are nearing completion.
![121st_St_and_Hoosier_Rd_RAB_Detour-1[1]](https://fisherscommunitycenter.com/wp-content/uploads/sites/10/2025/05/121st_St_and_Hoosier_Rd_RAB_Detour-11-1-1024x791.png)
Indoor Facility Updates
- All three large play structure towers in our Indoor Playground area have been installed; internal components are in progress.
- Finish flooring throughout the building is scheduled for completion by mid-July.
- The hardwood gym floor is complete in one upstairs group exercise room; gym installation is underway and will be done by mid-June.
- Casework installation and final painting are ongoing throughout the building.
- Permanent lighting has been turned on in many areas.
- Installation of finish doors is in progress.
Latest Drone Footage of Construction Site
Latest Drone Footage of Construction Site