June Construction Updates

Road & Site Work

  • Hoosier Road & 121st Street Roundabout:
    • The intersection is now closed for roundabout construction.
    • Closure Duration: May 29 – August 5 (HSE summer break).
    • This is a full intersection closure to accelerate construction.
    • The roundabout will include raised and striped pedestrian crossing speed tables on all four legs, ensuring safe access for pedestrians and cyclists entering the campus.
  • Site Grading & Landscaping:
    • Crews are using heavy equipment to complete final grading, install underground utilities, plant trees and landscaping, and begin irrigation installation.

Aquatics Center Progress

  • The pool slide has been installed on the exterior of the building.
  • Tile work and mechanical component installation for the pools are nearing completion.

Indoor Facility Updates

  • All three large play structure towers in our Indoor Playground area have been installed; internal components are in progress.
  • Finish flooring throughout the building is scheduled for completion by mid-July.
  • The hardwood gym floor is complete in one upstairs group exercise room; gym installation is underway and will be done by mid-June.
  • Casework installation and final painting are ongoing throughout the building.
  • Permanent lighting has been turned on in many areas.
  • Installation of finish doors is in progress.

Latest Drone Footage of Construction Site

Latest Drone Footage of Construction Site